Short answer: a rack power distribution unit (PDU) is the power strip of a server rack, built for racks. The four common categories differ in what they tell you and what they let you do: basic PDUs only distribute power; metered PDUs add a local load display; monitored PDUs report measurements over the network; switched PDUs additionally let you turn individual outlets on and off remotely. Choose by whether you need visibility, remote reporting, or remote control — in that order.

The four categories

Manufacturer documentation (for example Tripp Lite's PDU selection white paper) describes the same four-way split: basic, metered, monitored and switched. Category names and exactly which measurements or controls are included vary by manufacturer and model, so check the exact datasheet. In plain terms:

  • Basic: outlets and a breaker. No measurement. Fine where loads are known, small and someone is on site.
  • Metered: a display of current draw, so you can see how close the unit is to its limit before adding equipment. Read-only: you can see the load, you cannot control outlets.
  • Monitored: measurements available over the network, useful for spotting a growing load or a dead device from elsewhere.
  • Switched: per-outlet remote on/off as well as monitoring, mainly used to power-cycle a hung device without visiting the rack, and to sequence start-up after an outage.

Sizing without folklore

Add up the actual watts of what will be plugged in (labels state maximums; measured draw is usually lower), and keep the total within the PDU and circuit rating with headroom for start-up. This page deliberately states no universal percentage rule, because continuous-load rules and derating requirements come from your local electrical code and the equipment documentation, not from a web page. If in doubt, a licensed electrician sizes the circuit; this page gives no wiring instructions.

Where PDUs meet the rest of this reference set

Network modules are covered in SFP vs SFP+ vs SFP28 and the optical transceiver guide. For turning watts and hours into energy cost for a small rack or home lab, the appliance running-cost calculator works for rack loads too — enter your measured watts, hours and your own tariff.

Sources

Numbers on this page are worked examples from the stated assumptions, not tests of any product. Always check your own equipment labels and manuals.